UAE E-Invoicing Readiness Planner

See when to start each stage of your implementation, counted backwards from your mandatory go-live date. Your selections save in your browser.

Your compliance phase

Not sure which phase? Take the assessment →

Project complexity

To go live by 1 Jan 2027, a standard project needs about 23 weeks, but only 17 weeks remain, roughly 6 weeks behind an ideal schedule. Start now and compress testing where you safely can.

ERP readiness & data cleanup

24 Jul 202621 Aug 2026

Inventory your invoice data, standardise master data, and map fields to the PINT AE format. Fix gaps before anything else starts.

~4 weeksWindow passed

Select & appoint an Accredited Service Provider

21 Aug 202618 Sept 2026

Shortlist MoF Accredited ASPs for your ERP, run an RFP, and sign. This stage must finish by the statutory appoint-by deadline.

~4 weeksShould be underway nowStatutory deadline: 30 October 2026

ERP ↔ ASP integration build

18 Sept 202613 Nov 2026

Connect your ERP to the ASP (API, SFTP, or connector) and build the PINT AE mapping and validation.

~8 weeks

Sandbox testing & UAT

13 Nov 202618 Dec 2026

Transmit test invoices through the MoF sandbox, validate end-to-end, fix issues, and get user-acceptance sign-off.

~5 weeks

Go-live cutover & stabilisation

18 Dec 20261 Jan 2027

Switch to live transmission, monitor acknowledgements, and stabilise day-to-day operations.

~2 weeks

Your fixed regulatory deadlines

30 Oct 2026

Appoint an ASP by

1 Jan 2027

Full compliance / go-live

Based on MoF Ministerial Decision No. 244 of 2025, as amended by MoF Ministerial Decision No. 66 of 2026, last verified 19 August 2026. Always verify the current rules with the Ministry of Finance / Federal Tax Authority.

This planner shows when to do each stage. For what to do inside each one, the task-by-task detail, use the compliance checklist alongside it.

Stage durations are planning estimates based on typical UAE deployments, scaled by the complexity you selected; your real timeline depends on your ERP, data quality, and provider. The deadlines themselves are fixed regulatory dates.